Wednesday, March 14, 2012

Latest Photos of the Kitchen, Bridge, Courtyard & Roof

The courtyard, resident kitchen, bridge and games room, lounge and central stairway should all be completed by the 24th. Here are the latest shots.



Quite a view!



A tribute to St Patrick's Day, our proud Irish bridge builders!
The courtyard takes shape - timber and tiles
Central stairway down to the dining room
Roof with the louvres installed

Thursday, March 1, 2012

Steady Progress on the Roof & Courtyard

I haven't posted for two weeks, but O'Week has kept us all busy. Progress on the building has been good. While visually it has been hard to see the dramatic progress of some weeks, a great deal of work has been done on the courtyard floor, the Games Room and, the Lounge & Kitchen. As well, work on the louvres that protect the sides of the roof from rain has been underway. The engineering residents have had a field day observing the action form the balconies. All the while life in the common rooms and dining room has returned to 'normal' (if we ignore the noise and zones that residents can't access). However, completion of all spaces is expected within two to three weeks. Key achievements in the last two weeks are:

The courtyard slab floor has now been poured
Tiling is set to commence
The games room is taking shape with most of the glass walls installed
The ground floor apartments for visiting scholars and guests have been completed
The shared kitchen is almost ready for use

The photos below give some sense of progress.

Games Room Taking Shape
Completing the Courtyard Floor
New College Viewed from the top of the NCV


Normal O'Week Life in the Common Rooms




Friday, January 27, 2012

Roof is taking shape

The refurbishment project is on a four day break at the moment due to the Australia Day holiday and normal industry practices that require a rostered day off following a public holiday and no weekend work. This was factored into the work program. Progress overall has been good. The photos below show one of the many rooms that are nearing completion. Progress has been good with the rooms and common rooms and this work is on schedule.


The roof and courtyard are perhaps a day or two behind, but the structure is taking shape. Rain and some other challenges on site caused by the complexity of the project have slowed progress a little, but the work is coming along well. The image below shows that about 50% of the main roof structure is in place. Work on the attachment system for the glass and polycarbonate is also underway which will allow some cladding to occur soon. The courtyard floor cannot be sealed and tiled until more of the structure is in place. However, the surface is prepared and all new penetrations for the stairs and ventilation are done. The shared kitchen is also taking shape (and it's huge!). 

Wednesday, January 18, 2012

Games Room & Atrium Roof Take Shape

The last week have seen some major milestones met in relation to a number of critical path elements in the refurbishment.  Lipman has made excellent progress in relation to the courtyard, games room and roof. Below are a number of shots taken yesterday which show some key achievements.

1. The framework for Games room, lounge and stairway entrance were completed

Above: This shot gives a sense of the scale of the Games room

2. The courtyard skylight holes have been in-filled (note far right partially covered there is a section for one panel of glass floor skylights)


Above: The Skylights have gone and the concrete in-fills poured

3. The first elements of the roof structure arrived on site and the first installation occurred (the installation of the rest of the columns should be completed today).

Above: The first of the 8 columns go in

As well as the above, good progress is being made in the rooms and common rooms. Most rooms are now carpeted, most have some joinery installed, and the first carpet for halls and common rooms is going down. The work on fire safety is well advanced with a large part of the sprinkler system in place on all floors. All in all, progress is good and Lipman and its staff are working valiantly to meet our tough deadlines. In spite of the unpredictable weather the project is on track except for a few non-critical path elements such as the guest bedrooms downstairs.

Above: Rooms nearing completion; this one on level 3 is having the pin board added (carpet is covered)