Wednesday, January 18, 2012

Games Room & Atrium Roof Take Shape

The last week have seen some major milestones met in relation to a number of critical path elements in the refurbishment.  Lipman has made excellent progress in relation to the courtyard, games room and roof. Below are a number of shots taken yesterday which show some key achievements.

1. The framework for Games room, lounge and stairway entrance were completed

Above: This shot gives a sense of the scale of the Games room

2. The courtyard skylight holes have been in-filled (note far right partially covered there is a section for one panel of glass floor skylights)


Above: The Skylights have gone and the concrete in-fills poured

3. The first elements of the roof structure arrived on site and the first installation occurred (the installation of the rest of the columns should be completed today).

Above: The first of the 8 columns go in

As well as the above, good progress is being made in the rooms and common rooms. Most rooms are now carpeted, most have some joinery installed, and the first carpet for halls and common rooms is going down. The work on fire safety is well advanced with a large part of the sprinkler system in place on all floors. All in all, progress is good and Lipman and its staff are working valiantly to meet our tough deadlines. In spite of the unpredictable weather the project is on track except for a few non-critical path elements such as the guest bedrooms downstairs.

Above: Rooms nearing completion; this one on level 3 is having the pin board added (carpet is covered)

 


Saturday, December 31, 2011

The furniture begins to arrive

Progress continues at New. It has been encouraging to see lots of the rooms taking shape. Some are now receiving their joinery. The first batch of shelves arrived yesterday and units will be arriving daily for some time. Level 3 has progressed most with all services in place for the rooms, carpet well advanced and painting and fit-out commenced. Levels 1 & 2 are a little behind the 3rd floor, but all rooms are stripped, rendering completed where needed and services under way.

The joinery begins to arrive for bedrooms
The first pieces of joinery are going in (new shelves)
Services in place and carpet on the way on level 2

Painting the ceilings on level 3

Progress continues to be good in the courtyard. The skylights are all removed and the rest of the courtyard around them will be stripped soon as well as the concrete infills completed. The challenge with this work is to ensure that no water penetrates, so the stripping of the tiles is a progressive affair with covering (hence the frames) at the end of each day to keep water out.



The skylights have gone!

Progressive clearing of the courtyard.

HAPPY NEW YEAR EVERYONE!